As-built deviation drawing: structures against design per SP 70 and SP 45

The surveyor loads the DWG or DXF plan used for setting out and the raw total station export. The tool lands the points on the columns and piles of the drawing, computes the bottom and top shift from the faces, takes the tolerance for the structure type and writes the verdict with the code clause. Out come the same drawing with arrows per GOST R 51872-2024, a deviation statement and a DXF for CAD.

Data current as of 2026-09-26

Open the calculator → Free, no sign-up · interface in Russian

Standards

Tolerances per SP 70.13330.2012 (tables 5.12 and 6.1, rows 3 and 11 of table 6.1 as amended by Amendment 5) and SP 45.13330.2017 (tables 6.3 and 12.1 as amended by Amendment 2). Drawing conventions per GOST R 51872-2024.

Input

Structure type, the DWG or DXF plan and the total station export: point name, X, Y, H in metres, in the same coordinate system as the drawing. Without a drawing a table of design and surveyed coordinates works.

Output

Deviations in millimetres, a verdict per tolerance with the clause, level spread over the area, a drawing, an XLSX deviation statement, a DXF drawing.

What it does

Price

Free in full, no sign-up and no payment.

Open the calculator →

Questions

What do I load?

The DWG or DXF plan used for setting out and the raw total station export: point name, X, Y, H. Column faces are shot at the bottom and the top, piles at the head. The drawing may be in millimetres or metres, and the X and Y order of the survey file is detected.

Is the drawing stored on the server?

No. A DXF is read in the browser. A DWG goes to the server only to be converted to DXF and is deleted at once. The calculation receives only the outlines of the structures hit by the points and the points themselves. For the DXF export the part of the plan around the surveyed structures goes to the server to build the file and is not kept after the response.

Where do the tolerances come from?

From SP 70.13330.2012 and SP 45.13330.2017 for the chosen structure type. The values were checked against the code text, every verdict cites the table and item.

Why is the deviation split in two?

Each axis mark is checked across its own axis, so the tolerance is compared with the deviation along the building X and Y axes separately. If the grid is rotated against the coordinate system, enter the bearing of the X axis.

Are header fields and signatures filled in?

Yes. The company details and signatories from the letterhead panel go into the XLSX export and the print. The coordinate and height systems, the instrument and the setting-out base go into the drawing notes.