ISKRIT / Construction site / Cumulative log (KS-6a)
Construction site
Cumulative record of completed work, form KS-6a
The tool keeps a running total for the project: it adds the quantity completed in the reporting period to the quantity completed earlier, then computes the total since work began, the balance against the design, and the percentage of progress. Lines whose running total exceeds the design quantity are flagged separately.
Standards
Layout follows the standard KS-6a form (Goskomstat of Russia resolution 100 of 11 November 1999).
Input
Lines: code, description, unit, design quantity, completed earlier, quantity in the reporting period, unit price.
Output
Total since work began, balance, progress percentage, status per line, value completed, schedule totals, and XLSX export.
What it does
- Running total for every line
- Balance against the design and percentage of progress
- Lines above the design quantity flagged
- Value completed in the period and since work began
- Excel upload and XLSX export
Free and full version
Free
- Code-based calculations with no run limits
- Input validation and printable results
- Works instantly, no sign-up required
Full version
- Save projects and reporting periods
- Carry the previous period total into the completed earlier column
- Import large schedules from Excel
- Period history per project
Questions
Where does the completed earlier column come from?
From the previous period cumulative record, specifically its total since work began column.
What counts as an overstatement?
A line whose total since work began exceeds the design quantity. Such lines get their own status.
Are the form header fields filled in?
No, the tool computes the tabular part: quantities, running totals, balances, and values.