Area from coordinates calculator: shoelace formula for survey plots
Updated: September 30, 2026 · ISKRIT
The area of a plot from its corner coordinates comes from the shoelace (surveyor's) formula: twice the area equals the sum of Xi · Yi+1 - Xi+1 · Yi taken around the boundary. The calculator below takes grid coordinates in metres or latitude and longitude pasted from a web map, and returns the area in square metres, hectares, acres and square feet together with the perimeter.
Calculator
How it works
Shoelace formula. For every vertex multiply its X by the Y of the next vertex and subtract the X of the next vertex times its own Y. The sum over all vertices is twice the area with a sign that shows the direction of travel, so the absolute value is taken. The order of the two coordinates in a line does not change the area: easting and northing or northing and easting give the same result.
Vertex order. Enter the corners one after another along the boundary, clockwise or anticlockwise. If the order is mixed up the outline crosses itself and the area is wrong. The first corner does not need to be repeated at the end.
Latitude and longitude. Geographic coordinates are converted to metres on the WGS84 ellipsoid at the mean latitude of the plot, where a degree of latitude and a degree of longitude have different lengths. For plots up to tens of kilometres across the difference from a full ellipsoidal computation is below a hundredth of a percent. Lines such as "51.507351, -0.127758" can be pasted as they come from a map.
Legal area. Title documents usually state the area computed from the projected grid coordinates of the boundary survey. Use those coordinates for legal work; points picked on a map are good for estimates.
Worked example
Corners, easting and northing in metres: (512040.00, 6210300.00), (512070.00, 6210300.00), (512078.50, 6210345.20), (512035.20, 6210351.00). Shifted to the first corner they become (0, 0), (30, 0), (38.5, 45.2), (-4.8, 51.0). The shoelace terms are 0, 1356, 2180.46 and 0, the sum is 3536.46, and the area is 3536.46 / 2 = 1768.23 m², which is 0.1768 ha or 0.4369 acres.
Questions
How many points are needed? At least three. The outline closes by itself.
How do I convert to acres? One acre is 4046.856 m² and one hectare is 10 000 m². The calculator shows all units at once.
Why does my map measurement differ from the deed? Points picked on a map are off by metres, while the deed area comes from the boundary survey coordinates.
Cut and fill volumes from survey points inside a boundary are computed by the earthwork volume calculator.
Measurement uncertainty calculator: GUM budget with Type A, Type B and expanded U
Bearing and distance from coordinates: survey inverse calculator
Rotating shift patterns: covering the posts and balancing the hours
Calibration intervals: setting them, shortening them, defending them
Turning an estimate into a bill of quantities that foots
Progress billing: percent complete, carry-forward and retention
Checking claimed quantities: the design schedule and the survey
Pile capacity from CPT: how the LCPC method reads a cone trace
Driven and bored piles: why the same soil gives different capacity
What belongs on a borehole log, and what quietly gets left off
Drawing a cross section: correlating layers between boreholes
From an AGS4 file to a laboratory summary: what the groups carry
Characteristic values: turning a set of test results into one number
Void ratio, porosity and saturation from one density test
When one soil layer is really two: splitting geotechnical units
ASTM D4254 minimum index density: procedure and Dr calculator
Relative density Dr and density index Id are not the same number
USCS classification step by step: ASTM D2487
Cu and Cc: what the two gradation coefficients actually tell you
Dual symbols in USCS: the 5 to 12 percent fines band
EN ISO 14688-1 against USCS: two different size ladders
AGS4 file validation: what the rules actually check
AGS4 syntax: the five rules that break a delivery
ASTM D2435 oedometer test: from the curve to Cc, mv and Eoed
Converting oedometer modulus to Young’s modulus
EN ISO 17892-5 and ASTM D2435: where the two diverge
ASTM D1196 plate load test: modulus and subgrade reaction
DIN 18134: Ev1, Ev2 and the compaction ratio
Ménard pressuremeter modulus: ASTM D4719 and EN ISO 22476-4
Hydraulic conductivity from a pumping test: Dupuit calculator and formulas
Shewhart control chart constants: A2, A3, B3, B4, D3, D4, d2, c4
The eight out of control tests on a Shewhart chart
Repeatability and reproducibility limits: where 2.77 comes from
How rebar cutting plans are optimised: the cutting stock problem
Cutting waste in rebar fabrication: what percentage is normal
Rebound hammer calibration: why the factory curve is not enough
Kerf and offcut: what a linear cutting plan has to account for
Earthwork volume from survey points: grid, TIN and cross sections
Fire load density: the formula, the calorific values and the traps
Explosive atmosphere zones 0, 1, 2 and 20, 21, 22 explained
Pollution charges per tonne: how the over-limit multiplier works
The Russian environmental fee: who pays, when, and how the advances work